Construction Mortgages in BC: How Draws Work When You Build

by Silvana Azurdia

A house built on your own lot is paid for in stages, so it's financed in stages too. This guide explains how a construction mortgage, also called a draw mortgage, works in BC: how lenders approve it, how draws, inspections and interest work, the rules on builders, owner-builders and the lien holdback, and how to budget for the months before you move in.

The short version

 

A construction mortgage is a short-term loan approved on your plans, timeline, budget and builder, then paid out in draws as the work reaches stages such as the foundation, framing and completion, usually after the lender inspects the progress. During the build, you generally pay interest only on what has been drawn, and the loan becomes a regular mortgage when the home is finished. In BC, a new home must be built by a licensed residential builder and covered by home warranty insurance, unless you have an Owner Builder Authorization from BC Housing, and the Builders Lien Act requires a 10% holdback. Budget for a contingency and for carrying costs, and talk to a mortgage professional and a lawyer before you sign a building contract.

How a draw mortgage works

 

BC Housing describes construction mortgages as short-term loans that owners use to finance building a new home. Instead of one advance on a completion date, the money comes in draws:

  • Milestones or percentages. Often a draw is paid when a stage is reached, such as when the foundation has been poured. Some lenders pay by the overall percentage of the project that's complete.
  • An inspection first. BC Housing says the lender usually requires an inspection before each instalment. One lender's published example starts with a draw for the lot, then pays after the foundation and backfill; the framing, roof, doors and windows; the electrical, plumbing, insulation and exterior; and when the home is 100% complete.
  • Interest-only payments. In that example, you make monthly interest-only payments on the balance drawn so far, and the first payment of principal and interest is due a month after the home is complete.
  • Variable or fixed. BC Housing notes that some lenders use a variable rate during construction, letting you lock in a fixed rate at or near completion, while others let you choose up front. Some charge a premium or fees for the rate.

If you're still looking for land, start with Buying a Lot to Build On in BC.

What lenders look at before approving

 

BC Housing says most lenders require detailed construction plans, a project timeline and a thorough budget, and that a preapproval can give you a sense of how much a lender would be willing to lend you. Expect questions about:

  • Who is building. A licensed builder under a written contract, or you as an owner-builder; ask early whether a lender finances owner-built homes.
  • The land and the build together. Lenders look at the whole project, so equity in a lot you already own can count toward your down payment. Ask how the lender will value the lot.
  • Default insurance. With less than 20% down, you need mortgage default insurance. CMHC insures new construction loans paid out in progress advances, with the usual minimum down payment of 5% of the first $500,000 of the lending value and 10% of the rest, on a value under $1.5 million. Any equity in the land must stay in the project.

Draw schedules, fees and rates differ between lenders, so compare them; see Mortgage Broker or Bank?

Draws, cash flow and your building contract

 

A draw is paid after the work is done, so each stage has to be paid for first. BC Housing warns that a builder may expect to pay subtrades before the lender releases a draw, so have enough money available to pay the builder. Before you sign:

  • Match the schedules. Compare the payment schedule in your contract with the lender's draw schedule, and agree on how any gap will be covered.
  • Know the contract type. BC Housing says fixed-price contracts are usually only used for very small, simple projects, and cost-plus contracts, where the builder charges its costs plus a fee, for more complex ones. These should clearly define what counts as a cost.
  • Put changes in writing. BC Housing notes change orders often add time, and extra months mean extra interest and carrying costs.
  • Permits and inspections. The builder gets the building permit and works with the local building inspectors, separately from the lender's inspection before each draw.

The 10% lien holdback

 

A builders lien is a claim against your property by someone who worked on it or supplied materials and wasn't paid. BC's Builders Lien Act requires the person primarily liable on the contract, usually the owner, to hold back 10% of the value of the work. BC Housing says to keep it until the work is substantially complete and the holdback period has expired, with no liens filed.

  • Your lender may keep it. Under the Act, if your lender is a savings institution, such as a bank or credit union, and you authorize it to pay out the mortgage money, it can retain the holdback, and that counts as you keeping it. One lender's published terms say part of each draw is held back for a period set by provincial rules.
  • Liens affect your lender too. A mortgage advance made after a claim of lien is filed generally ranks behind that lien, so deal with any lien quickly, with your lawyer.

Hiring a Contractor in BC explains how long the holdback is kept and what to check before paying it out. Ask your lawyer or notary how it will be handled on your build.

Licensed builders, owner-builders and warranty

 

BC Housing says every new home in BC must be built by a licensed residential builder, who must arrange third-party home warranty insurance before getting the building permit. The New Home Registration Form is the proof the municipality or regional district looks for. I explain the coverage in New Home Warranty in BC.

To build without a licensed builder, you need an Owner Builder Authorization from BC Housing before construction starts:

  • Main conditions. An individual with a registered interest in the land, building for personal use, who builds or directly manages the construction and passes BC Housing's exam.
  • Living there. You must live in the home for at least a year after the occupancy permit before offering it for sale or rent, unless BC Housing allows a hardship exception.
  • Ten years of responsibility. There's no third-party warranty, you're personally liable for defects for 10 years, and if you sell within that time, you must give buyers an Owner Builder Disclosure Notice.

Budgeting: contingency, carrying costs and an example

 

BC Housing recommends a contingency fund of 10% to 20% of the total project budget for unexpected costs or changes: on a $600,000 build, $60,000 to $120,000. While you build, you also carry:

  • Your current home. Rent, or the mortgage on the home you live in. If you'll sell it, plan the timing with your lender; see Bridge Financing.
  • The lot itself. Property tax, utilities and insurance. Ask your insurer and your builder who insures the house while it's being built.
  • GST. It applies to construction, and CRA rebates can return part of it in some cases, including for a home built on land you own; see GST on New Homes in BC.

Here is an example of how interest builds up. Say you borrow $600,000 for the build in four draws of $150,000 about three months apart, at an example variable rate of 6%, charged on the amount drawn at 0.5% a month and assumed not to change:

  • Months 1 to 3: $150,000 drawn, about $750 a month in interest
  • Months 4 to 6: $300,000 drawn, about $1,500 a month
  • Months 7 to 9: $450,000 drawn, about $2,250 a month

That's about $13,500 in interest over nine months, compared with $27,000 if the full $600,000 had been advanced on day one. With the last draw at completion, the $600,000 becomes a regular mortgage: over 25 years at an example fixed rate of 4.5%, about $3,321 a month. The example leaves out the holdback, fees and any rate changes.

Questions buyers often ask me

 

How much down payment do I need to build a home?

It depends on the whole project, land and build together, and equity in a lot you own can count toward it. Below 20% down, you need default insurance: on a $900,000 lending value, for example, CMHC's minimum is $65,000.

Do I pay interest on the whole mortgage while my house is being built?

Generally not. You pay interest on what has been drawn so far, usually as monthly interest-only payments. Because the balance rises with each draw, a month of delay near the end of the build costs more interest than one near the start.

Can I build my own home in BC without a licensed builder?

Yes, with an Owner Builder Authorization from BC Housing, issued before construction starts. You must pass an exam and build or directly manage the work yourself, and you stay responsible for defects for 10 years, with no third-party warranty.

What happens if my build goes over budget?

Your mortgage is approved for a set amount, so overruns usually come from your own money. BC Housing recommends a contingency of 10% to 20% of the budget for unexpected costs and changes. If costs start climbing, talk to your builder and lender early.

When does a construction mortgage become a regular mortgage?

Once the home is complete and the final draw is paid. From then on, you make regular payments of principal and interest. If your rate was variable during the build, ask about locking in a fixed rate at or near completion.

Thinking about what to build? Read about laneway houses and coach houses, see what BC's zoning rules allow per lot, or try my mortgage calculator.

Planning to build on your own lot?

I can help you find a lot that suits your plans and connect you with mortgage professionals who arrange construction financing. Call or text 778-834-1706, email silvana@silvanaazurdia.ca or send me a message. Happy to help in English or Spanish.

This article is general information, not financial or legal advice. The details come from BC Housing, CMHC, CRA, BC's Builders Lien Act and a lender's published construction mortgage terms, and were current at the time of writing; each lender sets its own draw schedule, rates and fees. For BC Housing's guide to building with a builder, including construction mortgages and holdbacks, see Hiring a Builder in BC.