Before you take possession of a new home or presale condo, you and the builder walk through it together and write down anything damaged, unfinished or not working. That record matters long after you move in. Here is how the pre-delivery inspection works, what to check room by room, how the deficiency list relates to your 2-5-10 home warranty, and what to report once you live there, in your own home and in a strata's common areas.

The short version

 

The pre-delivery inspection, or PDI, is a walk-through with the builder before completion. Anything damaged, incomplete, missing or not working goes on the form, with a date for the builder to fix it, and you keep a copy and your own photos. The record matters: BC Housing says warranty providers generally rely on it to decide whether damage to finishes such as flooring, countertops and fixtures is covered, and damage that may have happened after you moved in will probably be treated as not covered. A builder's promise to fix something isn't the same as warranty coverage, so get dates in writing and follow up. After you move in, report new defects in writing to the warranty provider and the builder before each coverage period ends. In a strata, you report your unit; the strata corporation reports common property.

What the PDI is and who attends

 

BC Housing describes the pre-delivery inspection as a walk-through by the builder and the owner before completion, also called a new home orientation. Together you check that the terms of your contract have been met, the home is complete and the major items work. Builders often use the visit to explain how the home's systems run and to hand over manuals.

  • The form. Warranty providers usually have their own form, which may be called a completion certificate or a certificate of possession. Fill it in completely.
  • Who comes. You and the builder's representative. If you would like a licensed home inspector or someone else with you, ask the builder in writing well before the date, and check your purchase agreement. Home inspectors in BC are licensed by Consumer Protection BC, and their inspection is visual only; see Home Inspections in BC.
  • New or resale. A PDI is for a newly built home. When you buy a resale home, the closest equivalent is a final walkthrough, which you arrange through your offer.

For how a presale purchase reaches completion, see Buying a Presale Condo in BC.

Why the record matters for your warranty

 

Your 2-5-10 warranty covers defects, not normal wear and tear or damage, and BC's regulation lets a policy exclude damage caused or made worse by an owner or someone else. So a chip or scratch that isn't on the form can be hard to claim later. BC Housing's Residential Construction Performance Guide, which warranty providers have agreed to use to help judge claims, though they aren't bound by it, applies several of its standards only when the problem was reported at the PDI:

  • Windows and doors. Scratched or damaged glass and screens, chipped or scratched window and door frames, and dented or scratched exterior doors.
  • Floors. Dented hardwood, damaged laminate, and chipped or scratched ceramic or stone tile.

The same guide warns that a builder agreeing at the PDI to deal with something doesn't necessarily mean the warranty covers it. Warranty insurance is limited to defects as set out in the policy and the law. I explain the coverage itself in New Home Warranty in BC.

A room-by-room checklist

 

Bring your purchase agreement, your finish and upgrade selections, a flashlight and a phone charger to test outlets. Then open, run and look at everything:

  • Finishes. Floors, countertops, cabinets, tile and grout, trim, paint and drywall. Hold the flashlight low across surfaces to show scratches and chips.
  • Windows and doors. Each one opens, closes and locks, sliding doors roll and latch, seals sit flat and screens are there.
  • Appliances. The models match your agreement, nothing is dented, and each one runs.
  • Plumbing fixtures. Taps run hot and cold, toilets flush and refill, drains clear, nothing drips under the sinks, and tubs and sinks are free of chips.
  • Electrical. Every switch and outlet works, outlets with test and reset buttons trip and reset, the panel is labelled, and the intercom, doorbell and fobs work.
  • Heating and ventilation. The thermostat brings on the heat, bathroom fans and the range hood move air, and you know how to change any ventilation filters.
  • Balconies and patios. Railings are solid, the surface is undamaged and drains are clear.
  • Parking and storage. Your stall and locker match what your agreement says; see Parking Stalls and Storage Lockers.

BC Housing suggests taking pictures. I suggest a close-up of each item and a wider shot showing where it is.

How the deficiency list works

 
  • Be specific. "Chip in countertop, left of the kitchen sink" is easier to fix and to prove than "counter damaged".
  • Agree on dates. BC Housing suggests setting a reasonable date for the builder to complete the repairs.
  • Read before you sign. Check that every item you raised is on the form, and keep a copy with your warranty documents.
  • Check the fixes. When the builder says an item is done, look at it, and confirm what's finished and what's still open by email.

Read what your purchase agreement says about deficiencies at completion before the PDI. If major items are unfinished, ask your lawyer or notary about your options before completion; don't hold back money or refuse to complete on your own.

After you move in: new defects

 

Some problems only show up once you live in a home. Under BC's minimum coverage, defects in materials and labour are covered for 12 months (15 months for strata common property); defects in the electrical, plumbing, heating, ventilation and air conditioning systems, and some in exterior cladding, windows and doors, for 2 years; the building envelope for 5 years; and the structure for 10 years.

  • Report in writing. Send notice in reasonable detail to both the warranty provider and the builder, as soon as possible and before coverage expires. A phone call, or a request to the builder alone, doesn't replace written notice to both.
  • Limit the damage. If something needs immediate attention, such as a leak, take reasonable steps to stop it getting worse. Check with the warranty provider before other repairs, since work by someone else may limit your claim.
  • Know what's normal. The performance guide treats condensation between the panes of a sealed window as a defect, but not some water in the window tracks or condensation on the glass surface, and it doesn't cover minor floor squeaks.
  • Walk through again. BC Housing suggests inspecting your home carefully before each expiry date.

Strata units and common property

 

In a strata, BC Housing says you report defects inside your unit, and the strata corporation reports defects in the common property. If you notice a common property problem, tell the strata council or building manager in writing.

  • Start dates differ. Your unit's coverage starts at first occupancy or transfer of title, whichever comes first. Common property coverage starts when the first unit is occupied or transferred, so in a large building it may already be running when you move in.
  • The handover. Under the Strata Property Act, the developer acts as the strata council until the first annual general meeting. It must hold that meeting during a six-week period that starts when 50% plus one of the units have been transferred to buyers, or nine months after the first transfer if that's earlier. There it must give the strata copies of documents including the common property warranties and manuals and the plans used to get the building permit.
  • Inspections. BC Housing suggests strata corporations have the common property inspected before each part of the warranty expires.

Who pays for repairs outside the warranty is covered in Strata Repairs in BC.

Questions buyers often ask me

 

Can I bring a home inspector to my pre-delivery inspection?

Ask the builder in writing, well before the date, and check your purchase agreement. If an inspector comes, choose one licensed by Consumer Protection BC, and expect a visual inspection that looks for workmanship and damage, not behind finished walls.

What if I find a scratch or chip after I move in?

If it wasn't recorded at the PDI, it may be treated as damage that happened after occupancy, which the warranty generally doesn't cover. You can still ask the builder. Defects, as opposed to damage, stay covered for their warranty periods.

Does the builder's promise to fix something mean the warranty covers it?

Not necessarily. BC Housing's performance guide says warranty coverage is limited to defects under the policy and the law. Get the builder's commitment in writing with a date, and follow up by email until it's done.

Can I delay completion until the deficiencies are fixed?

Not on your own. Check what your purchase agreement says about completion and deficiencies, since refusing or delaying without a right to do so can put you in breach of the contract. Ask your lawyer or notary before completion if something major is unfinished or not working.

Who reports problems in the hallways, roof or parkade of my new building?

The strata corporation, since those areas are usually common property. Tell the strata council or property manager in writing, with photos. Until the first annual general meeting, the developer acts as the council, so the report goes to the developer.

Buying new? See how GST on new homes works, or read Moving into a Condo for move-in fees and elevator bookings.

Getting ready for your PDI?

I can help you prepare for your pre-delivery inspection, go through your deficiency list and follow up with the builder on what's still open. Call or text 778-834-1706, email silvana@silvanaazurdia.ca or send me a message. Happy to help in English or Spanish.

This article is general information, not legal advice. The details come from BC Housing's consumer guides, warranty pages and Residential Construction Performance Guide, the Homeowner Protection Act Regulation, the Strata Property Act and Consumer Protection BC, and were current at the time of writing; your purchase agreement and warranty policy set out your own terms. For BC Housing's steps for reporting a defect, see home warranty insurance claims.

Silvana Azurdia
Silvana Azurdia

Agent BCFSA 166340

+1(778) 834-1706 | silvana@silvanaazurdia.ca

GET MORE INFORMATION

Name
Phone*
Message