Renovating Inside Your Home: When You Need a Permit in the Lower Mainland

by Silvana Azurdia

Some interior projects need a building permit and some don't, and the line isn't drawn the same way in every city. This guide is for Lower Mainland homeowners planning work inside the house: what Vancouver, Burnaby and Surrey say needs a permit, what doesn't, the separate plumbing, electrical and gas permits, testing older homes for asbestos, the extra steps in a condo or townhouse, and why permits matter later.

The short version

 

Rules vary by city, so check yours before you start. Vancouver and Burnaby generally require a building permit for structural work and for moving or removing walls, and Surrey usually requires one for interior renovations and finishing a basement; Vancouver also lists moving plumbing, electrical or gas lines and adding a suite. Painting, new flooring and new cabinets generally don't need one. Plumbing, electrical and gas work need their own permits, and some work has to stay open until it is inspected. In an older home, test for asbestos before anything is disturbed. In a strata, get approval first; the city may require a permit too. Burnaby points out that owners are responsible for unpermitted work, even work done before they bought.

What usually needs a building permit

 

Each city publishes its own list, and the wording differs. Here is how three of them describe interior work:

  • Vancouver. A permit is generally needed for renovations that move interior walls or existing plumbing, electrical or gas lines, for structural repairs, for renovations that create new area, and for adding a secondary suite to an existing house.
  • Burnaby. Any alteration or removal of a building or structure requires a permit. Burnaby classes changes that don't add floor area as alterations, and its guides for them include adding bathrooms and building or taking down walls.
  • Surrey. A residential building permit is usually required for interior renovations and for finishing a basement.

In these cities, that covers most of what people mean by a renovation: opening up a kitchen, adding or moving a bathroom, finishing a basement and anything structural. Adding a suite brings its own requirements; see Legalizing a Basement Suite in BC. If you aren't sure about a project, Vancouver and Burnaby both suggest asking the city's building staff before you start.

What usually doesn't

 

Cosmetic work generally doesn't need a building permit:

  • Vancouver. Painting, replacing cabinets or flooring, unclogging drains, replacing an existing electric hot water tank, and replacing defective fuses, receptacles or switches.
  • Burnaby. Minor works such as replacing fixtures, cabinets and flooring, and painting the inside of your home.
  • Surrey. Replacing flooring and, in condo and townhouse units, changing flooring, cabinets or countertops or replacing plumbing fixtures in the same location.

So a kitchen or bathroom refresh that keeps the sink, toilet and shower where they are may not need a building permit, though for condos and townhouses Surrey notes that separate plumbing, electrical and sprinkler permits may still be required. Adding or moving lights or outlets is different: that is electrical work, which needs its own permit even when the cabinets don't.

Plumbing, electrical and gas permits

 

A building permit doesn't cover the trades. Surrey says separate plumbing and electrical permits are required for any plumbing and electrical work, and that you can apply for them only after the building permit is issued. Plumbing permits come from the city: Surrey issues them, and Vancouver says you need one to install, change or upgrade any part of a plumbing system.

Electrical and gas permits come from Technical Safety BC in most of the province. Burnaby and Vancouver issue their own electrical and gas permits, and Surrey issues its own electrical permits, so gas permits there come from Technical Safety BC. Technical Safety BC limits homeowner permits to people who solely own and occupy a single detached home with no suite; others hire a licensed contractor, who takes out the permit. Ask your contractor which permits the job needs and who will apply for each.

Inspections and the final sign-off

 

A permit comes with inspections. Burnaby inspects during various phases of a project to check the work against the approved plans, and says it is the permit holder's responsibility to arrange the inspections; your permit package lists the ones your project needs.

Timing matters. Coquitlam's inspection guide lists framing, and insulation and vapour barrier, among the inspections to book before work is concealed, and warns that work covered too early may need to be exposed for inspection, at the cost of delay and expense for the owner. When the work passes its final inspection, keep a copy of the record with the permit; buyers and insurers may ask for it.

Older homes: test for asbestos first

 

WorkSafeBC says asbestos is only harmful when materials containing it are disturbed, and renovation disturbs materials. When you hire anyone for a renovation or demolition, WorkSafeBC says homeowners must have the home tested for asbestos before work begins, by a qualified testing company or asbestos surveyor, and must hire a qualified asbestos abatement contractor if asbestos-containing materials are found. Abatement contractors must be licensed to operate in BC, and WorkSafeBC keeps an online registry of licensed contractors.

Cities can add their own steps. The District of North Vancouver, for example, notes that WorkSafeBC requires a hazardous materials survey in buildings built before 1990 before any renovation or demolition, and asks for written confirmation from a qualified person that hazardous materials were removed or contained, or inspections may not be booked. I cover the materials to watch for in Asbestos, Vermiculite and Lead Paint in Older BC Homes.

Condos and townhouses: the strata comes first

 

In a strata, start with the bylaws and the strata's written approval; I explain the process in Renovating a Condo: Strata Approvals and What to Ask First. Flooring is a common example: it may not need a city permit, but strata bylaws can set rules for underlay and noise; see Noise and Flooring in BC Condos. The city may need to approve the work as well:

  • Surrey. A building permit is needed to renovate a condo or townhouse unit where the work may include adding, moving or removing walls, changing any structural element, finishing a townhouse basement, or adding, moving or removing plumbing fixtures. A registered professional is required if any structural element or common property is affected.
  • Vancouver. Drywall repairs to fire separations in multi-unit residential buildings generally need a permit. The City's renovation checklist for multi-unit buildings says a strata council letter may be required, signed by the strata's chairperson to show it knows about and accepts the proposal.

Why permits matter later

 

Vancouver lists what can happen if you build without a permit: a penalty that is typically double the original permit fee, a stop to all work while an application is processed, and possibly removing work already done. Burnaby says homeowners are responsible for any unpermitted work on their property, even if it was done before they owned it, and Technical Safety BC says permits are often necessary for home insurance purposes.

When you sell, unpermitted work can affect disclosure, buyers and their lenders; I explain the options in Selling a Home with Unpermitted Work in BC. When you hire, put the permits in the contract: who applies, who books inspections, and that the final payment waits for the final inspection. I cover quotes, contracts and the lien holdback in Hiring a Contractor in BC.

Questions homeowners often ask me

 

Do I need a permit to replace kitchen cabinets and countertops?

Usually not a building permit. Vancouver and Burnaby list replacing cabinets as work that doesn't need one, and Surrey says the same for cabinets and countertops in condos and townhouses. Moving the sink or adding outlets is different, because that changes plumbing or wiring.

Can I take out a wall that isn't load-bearing without a permit?

Check with your city first. Vancouver's permit list includes renovations that move interior walls, Burnaby's alteration guides cover taking down walls, and Surrey requires a permit to remove walls in condo and townhouse units. None of these lists limits the rule to load-bearing walls.

Do I need a permit to finish my basement?

In Surrey, a residential building permit is usually required to finish a basement, including in a townhouse. In Vancouver, adding a secondary suite needs one. Expect plumbing and electrical permits as well if you add a bathroom or new lighting.

What happens if I renovate without a permit?

In Vancouver, you can face a penalty typically double the original permit fee, work has to stop while the application is processed, and you may have to remove work already done. The issue also stays with the house: Burnaby holds owners responsible, even for work done before they bought.

Do I need an asbestos test before a small renovation?

If you are hiring anyone and the work will disturb materials, WorkSafeBC says homeowners must have the home tested before work begins. The District of North Vancouver notes that WorkSafeBC requires a hazardous materials survey in buildings built before 1990 before any renovation work begins.

Planning other projects? See when decks and sheds need a building permit, home energy upgrades and older wiring and Poly-B pipes.

Buying a home that needs work, or renovating before you sell?

I can help you check a home's permit history and think through what a renovation involves before you buy or sell. Call or text 778-834-1706, email silvana@silvanaazurdia.ca or send me a message. Happy to help in English or Spanish.

This article is general information, not legal or professional advice. The details come from the cities of Vancouver, Burnaby, Surrey and Coquitlam, the District of North Vancouver, Technical Safety BC and WorkSafeBC, and were current at the time of writing; each city's rules differ and can change, so confirm with your city's building department before you start. For Vancouver's lists, see when you need a permit in Vancouver.

Silvana Azurdia
Silvana Azurdia

Agent BCFSA 166340

+1(778) 834-1706 | silvana@silvanaazurdia.ca

GET MORE INFORMATION

Name
Phone*
Message